top of page
fullsizeoutput_1f5.jpeg

Approach Lighting System with Sequence Flasher Category II Installations

ALSAF-II.jpg

Approach Lighting Systems are intended to provide a means of transition from instrument flight to visual flight for landing.

COMPLETED PROJECTS

Airfield Lighting Systems

Grissom Army Reserve Base, Grissom, IN

Contract # A1334-SC01

Customer Information

U.S. Army Engineer District

600 Dr. Martin Luther King Jr. Place Rm 821

Louisville, KY 40202-2239

Contact

Jordan Cole

Phone

406-499-6560

Contract Amount

$3,941,939.00

Job Scope

Various Airfield and Lighting Projects. Repair Taxiway C and G, runway and shoulder, overruns, airfield lighting system (phase A & B). 

Awarded

12/1/22

Start Date

4/1/23

Finish Date

10/28/23

ALSF-2 Replacement

George Bush Intercontinental Airport, Houston, TX

Contract # 697DCK-22-C-00148

Customer Information

Federal Aviation Administration

AAQ-500 Regional Acquisitions

10101 Hillwood Parkway

Fort Worth, TX 76177

Contact

Daniel Irungu

Phone

817-222-4550

Contract Amount

$8,734,859.60

Job Scope

Replacement and Hurricane Hardening-Runway 26L

Awarded

4/15/22

Start Date

8/22/22

Finish Date

11/01/23

Repair/Replace Airfield Lighting System

Grissom ARB, Grissom, IN

Contract # A1298-SC01

Customer Information

Royal Electric Company

8481 Carbide Ct. 

Sacramento, CA 95828

Contact

Jordan Cole

Phone

916-607-0776

Contract Amount

$1,635,035.00

Job Scope

Repair/Replace Airfield Lighting System

Awarded

02/01/2021

Start Date

04/12/2021

Finish Date

11/06/2021

ALSF II Installations-Phase II

Dulles International Airport, Chantilly, VA

Contract # EA.19.35120

Customer Information

PTSI Managed Services Inc. 

955 L'Enfant Plaza SW. Suite 6100

Washington D.C. 20024

Contact

Claudia Smith

Phone

210-861-0026

Contract Amount

$2,412,422.00

Job Scope

Runway 19L Approach Lighting System Flasher (ALSF-2) Installation

Awarded

01/22/2020

Start Date

Finish Date

06/09/2021

Contract Days

N/A

ALSF II Installations-Phase I

Dulles International Airport, Chantilly, VA

Contract # EA.19.35120

Customer Information

PTSI Managed Services Inc. 

955 L'Enfant Plaza SW. Suite 6100

Washington D.C. 20024

Contact

Lilana Kenna

Phone

210-861-0026

Contract Amount

$1,034,810.00

Job Scope

Runway 19L Approach Lighting System Flasher (ALSF-2) Installation

Awarded

08/12/2019

Start Date

10/19/2019

Finish Date

01/04/2020

Contract Days

N/A

ALSF II Upgrades

Sacramento International Airport, Sacramento, CA

Contract # 4428

Customer Information

Studebaker Brown Electric

6643 32nd St. STE 106

North Highlands, CA 95660

Contact

David Studebaker

Phone

916-678-4660

Contract Amount

$340,223.00

Job Scope

Installation of electrical wire, equipment and splices for ALSF station 0 thru 9. SIA RW 16R-34L 

Awarded

06/28/2019

Start Date

08/05/2019

Finish Date

10/21/2019

Contract Days

N/A

Northeast End Around Taxiway

Dallas Fort Worth International Airport, Dallas, TX

Contract # 9500623

Customer Information

Royal Electric Co.

8481 Carbide Court

Sacramento, CA 95828

Contact

Eric Gardner Sr.

Phone

N/A

Contract Amount

$575,095.00

Job Scope

Dallas Fort Worth International Airport required an ALSF shelter and light lane be modified as part of their end around project. DACO was hired to relocate the ALSF shelter and light lane stations as well has re-cable all of the existing ILS infrastrucres serving both parallel runways with new fiber and copper control wire. A new ILS support structure was attached to the existing ALSF shelter by expanding east. This new structure housed the fiber and communication electronics that served the ILS. DACO installed all the electronic and electrical infrastrure in the new shelter to replace the old comm structure.  

The existing ILS comm structure housed fiber and copper comm that served the entire east half of DFW. If this shelter was removed, then DFW would lose all of its ILS systems on the east side of the airport. DACO installed new fiber from the new shelter back to the ATCT and ran new fiber, heliax, 6 pair, 12 pair, 25 pair, 50 pair and 100 pair PE-39 copper shield cable to each affected facility on RW 13L-31R. A carful cutover plan was completed by DACO which allowed for both comm structures to be utilized and eliminated down time for the ILS systems to a day. Once the systems were running on the new fiber and comm, the old comm structure was demolished.   

DACO tested and terminated all comm wire.  

STA 23 and 24 of the ALSF were relocated to accommodate the new end around taxiway. New foundations, LIR structures were installed and tied into STA 22.  

Awarded

07/24/2017

Start Date

06/30/2018

Finish Date

05/18/2019

Contract Days

Runway 30

Oakland International Airport, Oakland, CA

Contract # AIP# 3-06-0170-64

Customer Information

Board of Port Commissioners 

Port of Oakland

530 Water Street

Oakland, CA 94607

Contact

Chris Bayne

Phone

916-226-2100

Contract Amount

N/A

Job Scope

Construction of Runway Safety Area Improvements 

Awarded

01/15/2014

Start Date

N/A

Finish Date

N/A

Contract Days

N/A

MALSF ON RWY 19

Washington Reagan National Airport, Washington, DC

Contract # DTFA07-01-T-04466

Customer Information

Federal Aviation Administration Southwest Region
2601 Meacham Blvd
Fort Worth, TX, 73137

Contact

Brad Logan

Phone

817-222-4395

Contract Amount

$839,420.00

Job Scope

Construction of a MALSF on Runway 19.

Awarded

09/09/2005

Start Date

06/22/2005

Finish Date

11/05/2005

Contract Days

60

CAT II/III ILS & ALSF-2, Runway 32R

Eppley Airfield, Omaha, NE

Contract # DTFACE-03-C-23052

Customer Information

Federal Aviation Administration Central Region
901 Locust Street
Kansas City, MO

Contact

Sharon Calebro

Phone

816-329-3113

Contract Amount

$1,172,312.00

Job Scope

Install access road, EES, fuel storage tank, foundations, equipment buildings, engine generator, conduit and cabling. Trench and install cable, lightning protection system, LOC antenna pedestals and raceway, ground check markers. This is for Glide Slope, Localizer/DME, Middle Marker and RVR site.

Awarded

09/15/2003

Start Date

11/05/2003

Finish Date

10/29/2004

Contract Days

210

Airfield Lighting Upgrade

Ft. Campbell Army Air Base, Ft. Campbell, KY

Contract # DABK09-03-C-0024

Customer Information

All Cities Enterprises
9005 3rd & Tennessee
Ft. Campbell, KY, 42223

Contact

Addie Lannom

Phone

931-431-0960

Contract Amount

$1,323,115.00

Job Scope

Design Build ALSF-1

Awarded

10/31/2003

Start Date

11/04/2003

Finish Date

N/A

Contract Days

360

Construct NAVAIDS/RWY Lighting & Related Work

Harrisburg International Airport, Harrisburg PA

Contract # H02-125-1610

Customer Information

Trumbull Corp/Bruce & Merilee Electric Co.
P.O. Box 98100
Pittsburgh, PA, 15227-0500

Contact

Robert Cane, II

Phone

412-462-9300

Contract Amount

$1,580,408.00

Job Scope

Runway 13 ALSF-2 Approach Lighting System, touchdown zone light & base in existing pavement, 1-way, 2� PVC concrete encased conduit in ex. pavement.

Awarded

11/12/2003

Start Date

10/13/2003

Finish Date

06/11/2004

Contract Days

170

ALSF-I1/CAT III

Salt Lake City International Airport, Salt Lake City, UT

Customer Information

Airsys ATM ,Inc.
23501 West 84th Street
Shawnee, KS, 66227

Contact

Ken Brust

Phone

816-453-2600 Ext. 5511

Contract Amount

$885,062.00

Job Scope

.

Awarded

06/17/1991

Start Date

05/28/1991

Finish Date

01/30/1992

Contract Days

170

ALSF-II

Greer, SC

Contract # DTFA06-90-C-50047

Customer Information

Federal Aviation Administration Southern Region
1701 Columbia Avenue
College Park, GA, 30337

Contact

Phyllis Thames

Phone

404-305-5818

Contract Amount

$497,323.13

Job Scope

N/A

Awarded

N/A

Start Date

04/20/1990

Finish Date

N/A

Contract Days

270.5

ALSF-11/SSALR to Severe Runway 36

Washington National Airport, Washington, D.C.

Contract # DTFA05-89-C-50627

Customer Information

Federal Aviation Administration Eastern Region
Fitzgerald Federal Bldg, JFK International Airport
Jamaica, NY, 11430

Contact

Marie Gallo

Phone

718-553-3086

Contract Amount

$274,974.00

Job Scope

Installation of a power & Control substation, erection of LIR Towers, electrical wiring, splicing termination & testing cables.

Awarded

08/24/1989

Start Date

10/11/1989

Finish Date

07/25/1990

Contract Days

120

ALSF-I System/MALSR to Severe Runway 5

New Bedford Municipal Airport, New Bedford, MA

Contract # DTFA12-89-C-00348

Customer Information

Federal Aviation Administration New England Region
12 New England Executive Park
Burlington, MA, 01803

Contact

Larry Robins

Phone

781-273-7600

Contract Amount

$411,009.00

Job Scope

Furnish all labor, material & equipment for the Demolition & Removal of an ALSF-I System and Installation of a MALSR to serve Runway 5.

Awarded

07/01/1989

Start Date

07/11/1989

Finish Date

11/02/1989

Contract Days

90

MALSF/REIL

Yampa Valley Regional Airport, Hayden, CO

Contract # DTFA11-88-C-00184

Customer Information

Federal Aviation Administration
1701 Pacific Highway
South Seattle, WA, 98168

Contact

Barber Garner

Phone

206-431-2857

Contract Amount

$119,682.00

Job Scope

Construction of a MALSF on Runway 10 and relocation / Replacement of REIL on Runway 28

Awarded

N/A

Start Date

09/20/1988

Finish Date

07/17/1988

Contract Days

50

ALSF-II/SSAR & Localizer Replacement 

Newark International Airport, Newark, NJ

Contract # DFA05-87-C-50559

Customer Information

Federal Aviation Administration Eastern Region
Fitzgerald Federal Bldg, JFK International Airport
Jamaica, NY, 11430

Contact

Maria Gallo

Phone

718-553-3087

Contract Amount

$282,815.00

Job Scope

Construction of a ALSF-II / SALR & Localizer Replacement

Awarded

05/28/1987

Start Date

07/23/1987

Finish Date

11/17/1987

Contract Days

100

ALSF-II/SSALR/Threshold BAR/MALSR

Eppley Airfield, Omaha, NE

Contract # AIP 3-31-00062-03

Customer Information

Federal Aviation Administration Central Region
601 East 12th Street
Kansas City, MO, 64106

Contact

George Campbell

Phone

816-426-3052

Contract Amount

$292,807.74

Job Scope

Construction of Dual Mode ALFS-II/SSALR, R/W 14R & Threshold Bar, MALSR, R/W 32L

Awarded

06/06/1985

Start Date

08/31/1985

Finish Date

06/05/1986

Contract Days

270

ALSF-II

Los Angles International Airport, Los Angles, CA

Contract # DTFA08-85-C-00580

Customer Information

Federal Aviation Administration Western Pacific Region
15000 Aviation Blvd
Hawthorn, CA, 90291

Contact

C.L. Peterson

Phone

213-536-6173

Contract Amount

$288,740.00

Job Scope

Construct ALSF-II

Awarded

03/25/1985

Start Date

03/25/1985

Finish Date

08/12/1985

Contract Days

180