RAISE ASR-9 TOWER 77' Sarasota International Bradenton Airport, Sarasota, FL Contract# DTFAO6-01-R-50010 |
||
| Customer Information | ||
|---|---|---|
|
Federal Aviation Administration Southern Region 1701 Columbia Ave College Park, GA, 30337 |
||
| Contact | Phone | Contract Amount |
| Gail P. Edwards | (404) 305-5182 | $219,875.00 |
| Job Scope | ||
| Raise Airport Surveillance Radar Tower 77 feet at the Sarasota International Airport | ||
| Awarded Date | Start Date | Finish Date |
| 05/11/2001 | 07/10/2001 | 09/10/2001 |
| Contract Days |
||
| 60 | ||
MODIFICATION TO AIR SURVEILLANCE RADAR Various Locations, LA & TX Contract# DTFAO7-97-R-O3326 |
||
| Customer Information | ||
|
Federal Aviation Administration Southwest Region 2601 Meacham Blvd. Fort Worth, TX, 73137 |
||
| Contact | Phone | Contract Amount |
| Ellis C. Mack | 817-222-4396 | $89,760.00 |
| Job Scope | ||
| Provide labor and materials & equipment for ASR-9 additional grounding Grid at 12 ASR-9. (100% by DEG - no asbestos) | ||
| Awarded Date | Start Date | Finish Date |
| 10/15/1997 | 12/02/1997 | 01/09/1998 |
| Contract Days |
||
| 75 | ||
ASR-9 FACILITY Sachse, TX |
||
| Customer Information | ||
|
Federal Aviation Administration Southwest Region 2601 Meacham Fort Worth, TX, 76193 |
||
| Contact | Phone | Contract Amount |
| N/A | N/A | $466,240.00 |
| Job Scope | ||
| N/A | ||
| Awarded Date | Start Date | Finish Date |
| N/A | 09/14/1992 | 10/30/1992 |
| Contract Days |
||
| N/A | ||
INCREASE ASR TOWER HEIGHT Waterloo, IA Contract# 94122339526 |
||
| Customer Information | ||
|
Raytheon Service Company 1155 Adams Street Kansas City, KS, 66103 |
||
| Contact | Phone | Contract Amount |
| Bernard Gorman | 913-621-2800 | $74,802.00 |
| Job Scope | ||
| Increase height of ASR antenna tower, remove underground fuel storage tank and pour foundations for vaulted fuel storage tank and set a vaulted fuel storage tank in place on the foundation. | ||
| Awarded Date | Start Date | Finish Date |
| 07/25/1991 | 08/19/1991 | 09/18/1991 |
| Contract Days |
||
| 45 | ||
ASR-9 Barksdale Airport Base, Bossier City, LA Contract# DTFA07-90-C-02801 |
||
| Customer Information | ||
|
Federal Aviation Administration Southwest Region 2601 Meacham Blvd. Fort Worth, TX, 76193 |
||
| Contact | Phone | Contract Amount |
| Robert Jamison | 817-624-5575 | $217,947.00 |
| Job Scope | ||
| Conversion of Airport Surveillance Radar (ASR-5) to ASR-9 | ||
| Awarded Date | Start Date | Finish Date |
| 08/30/1990 | 10/31/1990 | 03/06/1991 |
| Contract Days |
||
| 90 | ||
ASR-9 Miami International Airport, Miami, FL Contract# 94482880158 |
||
| Customer Information | ||
|
Raytheon Service Company 3420 Norman berry Drive Hapevill, GA, 30354 |
||
| Contact | Phone | Contract Amount |
| N/A | N/A | $381,304.00 |
| Job Scope | ||
| N/A | ||
| Awarded Date | Start Date | Finish Date |
| 04/24/1990 | 05/14/1990 | 10/11/1990 |
| Contract Days |
||
| 129 | ||
ASR-9 MOD RUNWAY 14 Piedmont Trais International Airport, Greensboro, NC |
||
| Customer Information | ||
|
Raytheon Service Company 3420 Norman Berry Drive Hapeville, GA, 30354 |
||
| Contact | Phone | Contract Amount |
| Charles Powell | 404-768-0333 | $75,679.00 |
| Job Scope | ||
| Erection of airport sponsor self-supporting 40' tall tower section, relocation of existing 27' tall ASR tower with operation antenna atop 40' section & installation of a facility ground system & electrical work. | ||
| Awarded Date | Start Date | Finish Date |
| 08/01/1989 | 08/22/1989 | 09/26/1989 |
| Contract Days |
||
| 90 | ||
CONSTRUCT A NEW TOWER FOR THE ASR-7 RADAR Baton Rouge Metropolitan Airport, Baton Rouge, LA Contract# DTFAO7-87-C-O3979 |
||
| Customer Information | ||
|
Federal Aviation Administration Southwest Region 2601 Meacham Blvd. Fort Worth, TX, 76137 |
||
| Contact | Phone | Contract Amount |
| Charles Grimes | 817-222- | $78,575.97 |
| Job Scope | ||
| Construction of a New Tower for the ASR- 7 | ||
| Awarded Date | Start Date | Finish Date |
| 10/01/1987 | 05/23/1988 | 07/30/1988 |
| Contract Days |
||
| 60 | ||
ASR-9 Offutt Air Force Base, Omaha, NE Contract# DTFAO9-88-C-20511 |
||
| Customer Information | ||
|
Federal Aviation Administration Central Region 601 East 12th Street Kansas City, MO, 64106 |
||
| Contact | Phone | Contract Amount |
| Sharon Calabro | 816-426-3053 | $184,449.00 |
| Job Scope | ||
| Modification to the mechanical /Electrical system | ||
| Awarded Date | Start Date | Finish Date |
| 12/02/1987 | 01/07/1988 | 07/14/1988 |
| Contract Days |
||
| 120 | ||
ASR-9 RADAR Dullas International Airport, Chantilly, VA Contract# DFTAOS-87-C-SOS39 |
||
| Customer Information | ||
|
Federal Aviation Administration Eastern Region Fitzgerald Federal Bldg,JFK International Airport Jamaica, NY, 11430 |
||
| Contact | Phone | Contract Amount |
| Marie Gallo | 718-917-0791 | $194,164.00 |
| Job Scope | ||
| Remove equipment crushed stone 6' Surface, Install concrete pad for A/C Transformer, Power Plant & Load Bank, Interior Electrical Lighting Grounding, Underground fuel Tank, HVAC work, Remove old transformer, power plant - | ||
| Awarded Date | Start Date | Finish Date |
| 06/08/1987 | 09/14/1987 | 02/10/1988 |
| Contract Days |
||
| 159 | ||