"MALSR"

PAPI & MALSR RUNWAY 28
Riverton Regional Airport, Riverton, WY
Contract# DTFANMAC-10-C-00095
Customer Information
Federal Aviation Administration
1601 Lind Ave.
Renton, WA, 98057
Contact Phone Contract Amount
Darren Odegard 425-227-1551 $97,767.00
Job Scope
Installation of PAPI & MALSR stations on Runway 28
Awarded Date Start Date Finish Date
03/12/2010 06/30/2010 08/10/2010
Contract Days
   
45    
 
 
MALSF & MALSR RUNWAY CONSTRUCTION
San Francisco International Airport, San Francisco, CA
Contract# DTFAAC-09-C-00013
Customer Information
Federal Aviation Administration
6500 South MacArthur Blvd.
Oklahoma City, OK, 73125-4929
Contact Phone Contract Amount
Kelly Tillery 405-954-7831 $2,087,714.00
Job Scope
MALSF & MALSR on Runways 19L & 28L
Awarded Date Start Date Finish Date
03/04/2009 05/26/2009 06/05/2010
Contract Days
   
120 days on 19L & 180 days on 28L    
 
 
MALSR, Runway 1
New Castle County Airport, Wilmington, DE
Contract# DTFA07-01-D-04465/0001
Customer Information
Federal Aviation Administration
2601 Meacham Blvd.
Fort Worth, TX, 73137
Contact Phone Contract Amount
Brad Logan (817) 222-4395 $1,382,750.00
Job Scope
MALSR site prep, excavate and pour concrete foundation piers and equipment pads. Install MALSR equipment shelter, conduit and wiring, lightning protection, MALSR light stations, improve access road.
Awarded Date Start Date Finish Date
04/24/2006 06/20/2006 05/17/2007
Contract Days
   
120    
 
 
Improve Runway Safety Area, MALSR
San Diego International Airport, San Diego, CA
Customer Information
Diamond Lane Contractors
1850 Diamond St. Suite 103
San Marcos, CA, 92078
Contact Phone Contract Amount
Mike Adams (760) 471-0090 $877,717.00
Job Scope
Excavate and pour LOC foundation, install ductback and arrays, install new MALSR, catch basin, asphalt service road.
Awarded Date Start Date Finish Date
05/26/2006 06/09/2006 07/28/2006
Contract Days
   
60    
 
 
MALSR with Runway Alignment on Runway 22
Millington Municipal Airport, Millington, TN
Contract# DTFA07-01-D-04465/001
Customer Information
Federal Aviation Administration
2601 Meacham Blvd.
Fort Worth, TX, 73137
Contact Phone Contract Amount
Carla Brawley (817) 222-4331 $594,215.17
Job Scope
Excavation for concrete foundations and cables; installation of MALSR power, control shelter, and access road, grounding and lightning protection.
Awarded Date Start Date Finish Date
08/03/2005 10/04/2005 06/17/2006
Contract Days
   
178    
 
 
MALSR & RCO FOUNDATION
Jack Edwards Airport, Gulf Shores, AL
Contract# DTFA07-01-T-04466
Customer Information
Federal Aviation Administration Southwest Region
2601 Meacham Blvd
Fort Worth, TX, 73137
Contact Phone Contract Amount
Brad Logan 817-222-4395 $67,679.00
Job Scope
Raise 5 RAIL stations by furnishing and installing MG-30 and MG-40 towers and RCO foundation.
Awarded Date Start Date Finish Date
11/18/2004 01/24/2005 02/18/2005
Contract Days
   
23    
 
 
MALSR, RUNWAY 18
Miller International Airport, Mccallen, TX
Contract# DTFASW-03-R-04465/0002
Customer Information
Federal Aviation Administration Southwest Region
2601 Meacham Blvd
Fort Worth, TX, 76137-4298
Contact Phone Contract Amount
Rose Marie Mendoza 817-222-4338 $348,933.00
Job Scope
Construction of Medium Intensity Approach Lighting System (MALSR) with Runway Alignment Lights on Runway 13.
Awarded Date Start Date Finish Date
12/22/2003 01/20/2004 05/14/2004
Contract Days
   
112    
 
 
ILS & PAPI, RUNWAY 18; MALSR
Colonel James Jabara Airport, Wichita, KS
Contract# DTFA07-0-T-04466
Customer Information
Federal Aviation Administration Southwest Region
2601 Meacham Blvd.
Fort Worth, TX, 76137-4298
Contact Phone Contract Amount
Brad Logan 817-222-4395 $1,438,744.64
Job Scope
Perform grading, install concrete foundations, conduit and cabling. Install equipment shelters, antenna towers and antennas; EES, and access road, MALSR.
Awarded Date Start Date Finish Date
07/14/2003 10/14/2003 07/22/2005
Contract Days
   
315    
 
 
CAT I ILS, RUNWAY 19L; CAT I ILS, RUNWAY 19R; MALSR
Mid Continent Airport, Wichita, KS
Contract# DTFA07-01-T-04466
Customer Information
Federal Aviation Administration Southwest Region
2601 Meacham Blvd.
Fort Worth, TX, 76137-4298
Contact Phone Contract Amount
Brad Logan 817-222-4395 $839,672.16
Job Scope
Install reinforced concrete foundation for Glide Slope antenna tower, and piers and pads for localizer antenna. Erect Glide Slope antenna tower and install antenna. Install EES at Localizer antenna pad and Glide Slope new antenna tower and bond to existing shelter EES. Install conduit and cabling and ground checkpoints for Localizer facility, aggregate surfacing around antenna tower foundation. Disassembly of existing equipment. Disassembly of existing Outer Marker Tower and removal of antennas. Erect antenna tower and install antennas. MALSR.
Awarded Date Start Date Finish Date
07/14/2003 08/25/2003 07/11/2005
Contract Days
   
300    
 
 
INSTALLATION OF A MALSR FOR RUNWAY 27 AND AN ILS
Jack Edwards Airport, Gulf Shores, AL
Contract# DTFA07-02-T-04466
Customer Information
Federal Aviation Administration Southwest Region
2601 Meacham Blvd.
Fort Worth, TX, 76137-4298
Contact Phone Contract Amount
Brad Logan 817-222-4395 $814,121.88
Job Scope
Installation of a Medium Intensity Approach Lighting System equipment at Jack Edwards Airport.
Awarded Date Start Date Finish Date
07/09/2002 10/07/2002 08/04/2003
Contract Days
   
212    
 
 
INSTALLATION OF A MALSR FOR RUNWAY 32 AND AN ILS
Statesboro, GA
Contract# DTFA07-02-T-0446
Customer Information
Federal Aviation Administration Southwest Region
2601 Meacham Blvd.
Fort Worth, TX, 76137-4298
Contact Phone Contract Amount
Brad Logan 817-222-4395 $862,337.82
Job Scope
Installation of Medium Intensity Approach Lighting System (MALSR) equipment at Statesboro-Bulloch County Airport.
Awarded Date Start Date Finish Date
03/18/2002 04/02/2002 05/22/2002
Contract Days
   
60    
 
 
MALSR
North Bend Municipal Airport, North Bend, OR
Contract# DTFA11-02-R-00020
Customer Information
Federal Aviation Administration Acquisition Management Branch, ANM53A12
1601 Lind Ave. SW
Renton, WA, 98055
Contact Phone Contract Amount
Patricia Workman 425-227-2863 $309,411.00
Job Scope
Construct Medium Intensity Approach Lighting System with Rail. 1400' of the system was installed on an existing steel walkway over the water. Installed a 3500' duct bank with concrete manholes for medium voltage home run terminating at medium voltage sectionalizing cabinet. Construct Medium Intensity Approach Lighting System with Rail. 1,400 feet of the system were installed on an existing steel walkway over the water. Installed a 3,500 ft. duct bank with concrete manholes for medium voltage homerun terminating at medium voltage sectionalizing cabinet.
Awarded Date Start Date Finish Date
03/18/2002 04/02/2002 05/22/2002
Contract Days
   
60    
 
 
RUNWAY 01 MALSR LIGHTING SYSTEM
Greenville Downtown Airport, Greenville, SC
Contract# AIP #3-45-0026-08
Customer Information
Walker & Whiteside, Inc.
P.O. Box 5777
Greenville, SC, 29606-5777
Contact Phone Contract Amount
Jim Cox 864-242-4820 $158,276.00
Job Scope
Furnish and install threshold bar and light bases, tower foundations and towers, lightning and grounding system.
Awarded Date Start Date Finish Date
10/09/2000 01/09/2001 04/21/2001
Contract Days
   
180    
 
 
MEDIUM APPROACH LIGHTING SYSTEM, PAPI, RUNWAY AND TAXIWAY LIGHTING
Worthington Municipal Airport, Worthington, MN
Contract# AIP PROJECT #3-27-0116-05
Customer Information
W. Hodgcman & Sons, Inc.
1100 Marcus Street
Fairmont, MN,
Contact Phone Contract Amount
Mark D. Johnson 507-235-3321 $535,396.00
Job Scope
Construction of medium approach lighting system, PAPI, Runway and Taxiway Lighting
Awarded Date Start Date Finish Date
08/20/1971 08/29/2000 10/18/2001
Contract Days
   
160    
 
 
MEDIUM INTENSITY APPROACH LIGHTING SYSTEM RUNWAY 6
Dutchess County Airport, Poughkeepsie, NY
Contract# NO: EA18BO0109
Customer Information
Raytheon Service Company
990 Stewart Avenue Suite 610
Garden City, NY, 11530
Contact Phone Contract Amount
Pat Williams 516-228-8828 $629,734.46
Job Scope
Retrofit the existing Medium Intensity Approach Lighting System with Runway Alignment Indicator Lights
Awarded Date Start Date Finish Date
N/A 09/13/1999 05/17/2000
Contract Days
   
N/A    
 
 
ILS/MALSR
Shawnee Municipal Airport, Shawnee, OK
Contract# DTFAO7-97-C-O3317
Customer Information
Federal Aviation Administration Southwest Region
2601 Meacham Blvd.
Fort Worth, TX, 73137
Contact Phone Contract Amount
George Ramsey 817-222-4664 $429,620.00
Job Scope
Installation of Instrument Landing System & MALSR. (100% by DEG - no asbestos)
Awarded Date Start Date Finish Date
N/A 09/23/1997 06/18/1998
Contract Days
   
90    
 
 
REMOVAL & REPLACEMENT OF MALSR
Mt Comfort Airport, Mt Comfort, IN
Contract# GLAOOO94
Customer Information
Raytheon Service Company
10400 W. Higgins Road
Rosemont, IL, 60018
Contact Phone Contract Amount
Helen Landwer 847-699-8400 $17,253.00
Job Scope
Removal & reinstallation of the MALSR, Removal of existing threshold light foundations, install screw anchors as new foundations for the threshold lights. Replace existing cables from splice point to the threshold lights.
Awarded Date Start Date Finish Date
10/01/1996 11/18/1996 11/26/1996
Contract Days
   
12    
 
 
MALSR RUNWAY 33R
Baltimore Washington International Airport, Baltimore, MD
Contract# DTFAO5-96-C-50825
Customer Information
Federal Aviation Administration Eastern Region
Fitzgerald Federal Building, JFK International Airport
Jamaica, NY, 11430
Contact Phone Contract Amount
Glenn Fox McCarthy 718-553-3085 $324,970.00
Job Scope
Construction of foundations, Access roads and parking areas, installation of light towers, cables and other electrical work. (100% by DEG - no asbestos)
Awarded Date Start Date Finish Date
09/30/1996 10/21/1996 04/10/1997
Contract Days
   
120    
 
 
MALSR AT RUNWAY 14
Piedmont Trais International Airport, Greensboro, NC
Contract# 94482800166
Customer Information
Raytheon Service Company
3420 Norman Berry Drive
Hapeville, GA, 30354
Contact Phone Contract Amount
Charles Powell 404-768-0333 $169,526.00
Job Scope
Schedule I: Installation of MALSR P&C Building with equipment access Rd. Schedule II Removal of existing SSALR system from service & complete modification of MALSR direct-earth burial & overhead cables. Schedule III remove & transport to storage all existing GP-l & platform structures not utilized for the MALSR
Awarded Date Start Date Finish Date
N/A 11/14/1990 02/27/1991
Contract Days
   
85    
 
 
MALSR
Evansville Regional Airport, Evansville, IN
Contract# 94141987988
Customer Information
Raytheon Service Company
10400 W. Higgins Road
Rosemont, IL, 60018
Contact Phone Contract Amount
Helen Landwer 847-699-8400 $137,924.28
Job Scope
Remove existing SSALR, disconnection of all power & control cables to be abandoned, semi-flush threshold bar removal all light bars & flashers, Install MALSR, aiming of light bars, RAl flashing lights.
Awarded Date Start Date Finish Date
05/25/1990 07/09/1990 09/28/1990
Contract Days
   
60    
 
 
MALSR RUNWAY 09
Savannah International Airport, Savannah, GA
Contract# DTFA06-90-C-30012
Customer Information
Federal Aviation Administration
3400 Norman Berry Drive
East Point, GA, 30344
Contact Phone Contract Amount
Bette Cabot 404-763-7337 $74,967.00
Job Scope
Installation of a complete & operable MALS/RAIL system including EMT- mounted light structures, power & control station plot, direct-earth burial cabling, electrical & control equipment, construction of an access road with parking area, removal of existing ALS system
Awarded Date Start Date Finish Date
01/15/1990 04/04/1990 06/12/1990
Contract Days
   
60    
 
 
MALSR/REIL
Dannelly Field, Montgomery, AL
Contract# DTFA06-90-C-50045
Customer Information
Federal Aviation Administration Southern Region
1701 Columbia Avenue
College Park, GA, 30337
Contact Phone Contract Amount
Larry Cleveland 404-305-6700 $135,851.48
Job Scope
Schedule I, MALSR Runway 09 concrete work, cabling, station erection, & MALSR shelter installation. Schedule II, MALSR Runway 09 All work at sta 4+06, 2+06, relocated threshold, all cabling in the overrun. The existing ALSF-I substation, light structures, and remote control in ATCT shall be removed. Schedule III, REIL Runway 03 installation of REIL including threshold relocation, cabling, light installation, and radio control installation. Schedule IV, MALSR Runway 27 MALSR shelter including replacing the existing radio control with new radio control ATCT work is included.
Awarded Date Start Date Finish Date
12/14/1989 04/04/1990 07/28/1990
Contract Days
   
75    
 
 
INSTALL MALSR TO SERVE RUNWAY 03
Lynchburg Municipal Airport, Lynchburg, VA
Contract# DTFA05-89-C-50586
Customer Information
Federal Aviation Administration Eastern Region
Fitzgerald Federal Bldg, JFK International Airport
Jamaica, NY, 11430
Contact Phone Contract Amount
Peter Folan 718-832-8500 $160,914.00
Job Scope
Construction of foundations, trenching, electrical wiring, erection of LIR Towers, Installation of Equipment Shelter, Demolition, etc
Awarded Date Start Date Finish Date
09/20/1989 10/25/1989 01/25/1990
Contract Days
   
60    
 
 
MALSR AT RUNWAY 8
Laconia Municipal Airport, Gilford, NH
Contract# DTFA12-89-C-00348
Customer Information
Federal Aviation Administration New England Region
12 New England Executive Park
Burlington, MA, 01803
Contact Phone Contract Amount
N/A 617-238-7000 $466,895.00
Job Scope
furnish labor, material, equipment and supplies for the installation of a MALSR with runway Alignment Indicator Lights.
Awarded Date Start Date Finish Date
10/13/1989 10/25/1989 04/04/1990
Contract Days
   
120    
 
 
CONVERSION OF SSALR TO MALSR
Indianapolis International Airport, Indianapolis, IN
Contract# 94141962449
Customer Information
Raytheon Service Company
10400 W. Higgins Road
Rosemont, IL, 60018
Contact Phone Contract Amount
Helen Landwer 847-699-8400 $148,455.00
Job Scope
Work consists of the removal of existing simplified short approach lighting system with runway alignment indicator lights(SSALR) replacement of a MALSR, remove semi flushed threshold bar & 12 additional light bars on elevated structures.
Awarded Date Start Date Finish Date
10/11/1989 10/23/1989 05/03/1990
Contract Days
   
80    
 
 
MALSR SERVING RUNWAY 22L
Newark International Airport, Newark, NJ
Contract# DTFA05-89C-50645
Customer Information
Federal Aviation Administration Eastern Region
Fitzgerald Federal Bldg, JFK International Airport
Jamaica, NY, 11430
Contact Phone Contract Amount
Steve Barry 718-917-0791 $165,411.00
Job Scope
Construction of foundations, installation of Power & Control Substation, Electrical Wiring System
Awarded Date Start Date Finish Date
07/06/1989 08/22/1989 01/09/1990
Contract Days
   
65    
 
 
ALSF-I SYSTEM /MALSR TO SERVE RUNWAY 5
New Bedford Municipal Airport, New Bedford, MA
Contract# DTFA12-89-C-00348
Customer Information
Federal Aviation Administration New England Region
12 New England Executive Park
Burlington, MA, 01803
Contact Phone Contract Amount
Larry Robins 781-273-7600 $411,009.00
Job Scope
Furnish all labor, material & equipment for the Demolition & Removal of an ALSF-I System and Installation of a MALSR to serve Runway 5
Awarded Date Start Date Finish Date
07/01/1989 07/11/1989 11/02/1989
Contract Days
   
90    
 
 
MALSR
Ft. Lauderdale, FL
Contract# DTFA06-89B-50104
Customer Information
Federal Aviation Administration Southwest Region
3400 Norman Berry Drive
East Point, GA, 30344
Contact Phone Contract Amount
Phyllis Thames 404-763-7326 $16,944.31
Job Scope
Construction of a MALSR
Awarded Date Start Date Finish Date
05/05/1989 06/30/1989 10/12/1989
Contract Days
   
90    
 
 
MALSR
Bradford Regional Airport, Bradford, PA
Contract# DTFAO5-87-C-50533
Customer Information
Federal Aviation Administration Eastern Region
Fitzgerald Federal Bldg, JFK International Airport
Jamaica, NY, 11430
Contact Phone Contract Amount
Maria Gallo 718-553-3087 $130,979.00
Job Scope
Demolition of existing towers and substation, Installation of MALSR electronic equipment & Shed, installation of splicing termination of cables, install low impact resistance towers, aiming test, Glide Slope transformers.
Awarded Date Start Date Finish Date
06/16/1987 08/11/1987 11/14/1987
Contract Days
   
96    
 
 
MALSR
Baton Rouge Metropolitan Airport, Baton Rouge, LA
Contract# DTFAO7-86-C-O3853
Customer Information
Federal Aviation Administration Southwest Region
4400 Blue Mound Road
Fort Worth, TX, 76101
Contact Phone Contract Amount
Carmen Mondragon 817-877-2230 $126,070.00
Job Scope
Construction of a Medium Intensity Approach Lighting System with Runway Alignment Indicator Lights (MALSR) on Runway 22
Awarded Date Start Date Finish Date
N/A 10/01/1986 12/10/1986
Contract Days
   
90    
 
 
INSTALL MALSR THRESHOLD BAR
Butler Graham Airport, Butler, PA
Contract# DTFAO5-86-50459
Customer Information
Federal Aviation Administration Eastern Region
Fitzgerald Federal Bldg JKF International Airport
Jamaica, NY, 11430
Contact Phone Contract Amount
Michael Monahan 718-917-0791 $19,338.00
Job Scope
Construction of foundations, electrical work, Underground Cables, to Install MALSR Threshold Bar to serve RW/8
Awarded Date Start Date Finish Date
06/11/1986 06/18/1986 06/29/1986
Contract Days
   
30    
 
 
INSTALL AIRPORT LIGHTING, ILS LOCALIZER RELOCATION, ILS MIDDLE MARKER RELOCATION, MALSR EQUIPMENT RELOCATION, GLIDE SLOPE ANTENNA RELOCATION, VASI 6 RELOCATION
Tucson International Airport, Tucson, AZ
Contract# #3-04-0045-03
Customer Information
Granite Construction Company
P .0. Box 27557
Tucson, AZ, 85726
Contact Phone Contract Amount
Mark Boitano 602-748-8000 $717,244.00
Job Scope
Construction of Runway 11L/29R extension SE (2,250 x 150') including porous friction course, lighting, marking and associated taxiway, relocate NW threshold Runway 111/29R (3,250') including lighting, markings, and associated taxiway, relocate approach lighting, ILS VASI System and Air National Guard Aircraft Arresting System on Runway 11 L/29R provide extended Safety areas.
Awarded Date Start Date Finish Date
05/20/1986 06/05/1986 N/A
Contract Days
   
N/A    
 
 
ALSF-II/SSALR/THRESHOLD BAR/MALSR
Eppley Airfield, Omaha, NE
Contract# AIP 3-31-00062-03
Customer Information
Federal Aviation Administration Central Region
601 East 12th Street
Kansas City, MO, 64106
Contact Phone Contract Amount
George Campbell 816-426-3052 $292,807.74
Job Scope
Construction of Dual Mode ALFS-II/SSALR, R/W 14R & Threshold Bar, MALSR, R/W 32L
Awarded Date Start Date Finish Date
06/06/1985 08/31/1985 06/05/1986
Contract Days
   
270    
 
 
MALSR RUNWAY 26L MALSR
W.B. Hartsfield International Airport, Atlanta, GA
Contract# DTFA06-85-C-30470
Customer Information
Federal Aviation Administration Southern Region
3400 Norman Berry Drive
East Point, GA, 30344
Contact Phone Contract Amount
Phyllis Thames 404-763-7337 $114,561.76
Job Scope
Retrofit the Medium Intensity Approach Lighting System Runway 26L
Awarded Date Start Date Finish Date
08/07/1985 08/16/1985 11/22/1985
Contract Days
   
90    
 
 
ILS, GLIDE SLOPE/MALSR
Prescott Municipal Airport, Prescott, AZ
Contract# DTFAO8-84-B-O2236
Customer Information
Federal Aviation Administration Western Region
P.O. Box 92007, WWPC
Los Angeles, CA, 90009
Contact Phone Contract Amount
Cheryl Petersen 213-536-6173 $198,002.00
Job Scope
Construction ILS Localizer, Glide Slope, Middle Marker, DME and MALSR for Runway 21.
Awarded Date Start Date Finish Date
N/A 10/22/1984 03/17/1985
Contract Days
   
180    
 
 
EMERGENCY RECONSTRUCTION OF MALSR, RUNWAY 4 AND LOCALIZER, RUNWAY 22
Adams Field Little Rock, Little Rock, AR
Contract# DTFA07-90-C-02747
Customer Information
Federal Aviation Administration Southwest Region
2601 Meacham Blvd.
Fort Worth, TX, 73137
Contact Phone Contract Amount
Robert Jamison 817-222-5098 $234,162.00
Job Scope
Emergency repair and replacement of the MALSR and Localizer
Awarded Date Start Date Finish Date
01/23/1990 00/00/0000 03/03/1990
Contract Days
   
55    
 
 
MALSR
Guam International Airport, Agana, Guam
Contract# DTFAO8-87-C-45129
Customer Information
Federal Aviation Administration Western Pacific Region
15000 Aviation Blvd
Hawthorne, CA, 90291
Contact Phone Contract Amount
Barbara Benett 310-725-7548 $78,274.00
Job Scope
Install a Threshold Bar for a Medium Intensity Approach Lighting System with Runway Alignment Indicator Lights ( MALSR)
Awarded Date Start Date Finish Date
09/29/1987 N/A N/A
Contract Days
   
30    
 
 
RUNWAY 25 GLIDE SLOPE I MALSR
Jacksonville International Airport, Jacksonville, FL
Contract# BB6357
Customer Information
AIRSYS A TM
23501 West 84th Street
Shawnee, KS, 66227
Contact Phone Contract Amount
Twyla Cochran 913-422-2728 $260,377.00
Job Scope
Construction of Glide Slope & MALSR. Remove & Dispose of all growth & planting materials and site improvements as required. Minor leveling and grading
Awarded Date Start Date Finish Date
N/A N/A 04/04/1998
Contract Days
   
90    
 
 

Airport Lighting Systems

Airport Landing Systems